Back to Portfolio

Wind Farm, Corugea

Division Cranes
Location Corugea, Tulcea County
Services Earthworks & Utilities, Cranes
Client Enel Green Power Romania
Period 2010 – 2011

Corugea Wind Farm

Apolodor carried out civil works, foundations and roads for the farm’s 35 wind turbines. The work, which lasted almost 7 months, used a large amount of machinery (130-tonne crane, backhoe loaders, excavators, dump trucks, pile drilling rig) and a team of 200 employees.
Capacity: The farm has an installed capacity of 70 MW and was one of the major renewable energy projects developed by Enel Green Power in Dobrogea at that time.

Formular Apolodor Contact

    Contact form

    * Required fields.