Electroaparataj Factory

Division Demolition
Location Bucharest
Services Demolition
Client NEPI Rockcastle
Period 2012

The Electroaparataj electrical and electronic products factory

The demolition works began at the end of March and were completed in August, with all the buildings on the Electroaparataj site mechanically demolished. The whole range of excavators was used to demolish the former Electroaparataj electrical and electronic products factory, from the small IHI 17, used to demolish interior masonry, to the large Liebherr R 954 excavator.
The total volume demolished was 40,000 m³.

  • Project context: The demolition was necessary to clear the approximately 4-hectare site for the construction of the Mega Mall shopping centre.
  • Technology used: A fleet of excavators equipped with long booms and hydraulic shears was used to bring down the massive reinforced concrete structures of the industrial halls at an accelerated pace.
  • Current location: The site of the former factory is now home to Mega Mall Bucharest, inaugurated in May 2015.