The work was carried out using a technology introduced in Romania by our company back in 1998.



Given the great height of the chimney (120 m) and the fact that operating installations of the power plant were located in the immediate vicinity, and without disrupting activity, we used the fine, piece-by-piece demolition method. An Atlas Copco 2100 hydraulic demolition shear was used, mounted on a Liebherr LTM 1500 crane with a 150 m boom, and powered by the large Liebherr R 954 excavator via extended hydrostatic transmission lines. A system transmitting images captured by a camera placed at the top of the chimney helped the ground operator operate the demolition shear with maximum precision.
The operation took 30 days and is the most efficient demolition method for a structure of this height, being carried out in a very short time, without vibrations or disruption of activity within a 25 m radius, and under conditions of maximum safety.